Removal and demolition of substandard porch. North Devon
Removal and demolition of existing substandard porch 
Timber separated for recycling North Devon
Timber separated for recycling 
New foundation trench dug out North Devon
New foundation trench dug out 
c35 heavy mix concrete foundations poured, for new walls North Devon
c35 heavy mix concrete foundations poured, for new walls. 
Block course built to get above ground, with DPC and sole plate for timber frame North Devon
Block course built to get above ground, with DPC and sole plate for timber frame 
Timber frame erected with cut roof. Plyed battened and breathable felt installed North Devon
Timber frame erected with a cut roof, plyed battened and breathable felt membrane installed 
First fix electrical and plumbing, walls insulated using Recticel Wall Insulation Board. North Devon
First fix electrical and plumbing, walls insulated using Recticel Wall Insulation Board.  
Ceiling joists installed with 300mm insulation above. North Devon
Ceiling joists installed with 300mm thick roof insulation above.  
Stud wall and frame installed to make toilet area North Devon
Stud wall and frame installed to make toilet area 
Walls skim's and new door hung North Devon
Walls skim's and new door hung 
Skirtings primed and installed, timber frame knotted North Devon
Skirtings primed and installed, timber frame knotted 
uPVC windows and doors installed and glazed, North Devon
uPVC windows and doors installed and glazed 
New wall hung sink and mixer tap installed, with uPVC splashback North Devon
New wall hung sink and mixer tap installed, with a uPVC splashback 
Close coupled toilet installed with Altro nonslip flooring and decorated internals North Devon
Close coupled toilet installed with Altro nonslip flooring and decorated internals. 
Exterior roof tiled with dry verge edging, lead flashing, black gutters and down pipes. Walls clad with Cedral prefinshed lapped, wood finish cladding boards. North Devon
Exterior roof tiled with dry verge edging, lead flashing, black gutters and down pipes. Walls clad with Cedral prefinshed lapped, wood finish cladding boards.  
Project organised and managed by MJS Building Maintenance Ltd. for NDDC, Project over looked by Building Control and singed off, completed in a timely manner and to an agreed budget. 
Cloakroom extension completed in North Devon
Project undertaken and managed by MJS Building Maintenance Ltd. from demolition to completion of project. Project kept within budget and completed on time, working to a pre agreed schedule. 